In accordance with the Decree of the President of the Republic of Uzbekistan dated may 16, 2024 No. PP-286 “On approval of the investment program of the Republic of Uzbekistan for 2024 and the introduction of new approaches and mechanisms for managing investment projects" Almalyk MMC JSC is implementing 10 investment projects with a total value of $13 750.6 million, including:
- at the expense of own funds – $3829.2 million;
- Funds of RDF of Uzbekistan – $294.2 million;
- commercial bank loans – $22.1 million;
- foreign direct loans – $9 605.1 million.
The development of capital investments for 2024 is planned for $2 236.4 million., including:
- at the expense of own funds – $124.3 million;
- Funds of RDF of Uzbekistan - $70.8 million;
- foreign direct loans – $2 041.3 million.
INFORMATION (As per october 1, 2024) mln USD |
|||||||||
№ |
Name of projects |
Total cost of the project |
Basis for implemen-tation |
Project capacity |
Project period |
CAPEX for 2024 |
CAPEX for January-July |
Actual CAPEX for January-July |
% |
|
In total |
13 750,6 |
|
|
|
2236,4 |
1376,3 | 1419,6 | 103,1 |
1 |
Development of "Yoshlik I" mine (stage 1) |
4620,4 |
RP-2807 dated 01.03.2017, RP-4731 dated 02.05.2020 |
Processing up to 60 million tons of copper-molybdenum ore per year |
2017-2024 |
1179,0 |
938,8 | 931,7 | 99,2 |
2 |
Construction of a new metallurgical complex as part of the Development of the "Yoshlik-I" mine (stage 1). |
2550.0 |
RP-2807 dated 01.03.2017, RP-4731 dated 02.05.2020 |
300 thousand tons of copper cathode |
2021-2027 |
392,0 |
137,7 | 142,0 | 103,1 |
3 |
Construction of the copper concentrator-4 and infrastructure facilities within the framework of the Development of the "Yoshlik I" mine (Stage 2). |
5300.0 |
RP-2807 dated 01.03.2017, RP-4731 dated 02.05.2020 |
Processing up to 60 million tons of copper-molybdenum ore |
2024-2028 |
190,0 |
6,1 | 122,4 | 2006,4 |
4. |
The program of reconstruction and stabilization |
357.5 |
RP-3954 dated 30.09.2018 |
stabilization of activity |
2018-2025 |
40,0 |
52,0 | 57,4 | 110,5 |
5. |
Development of Khandiza mine (second stage) |
102.9 |
RCM-317/11 dated 28.07.2023 |
650 thousand tons of ore per year |
2023-2028 |
15,0 |
10,2 | 10,1 | 99,2 |
6. |
Construction of a 500 MW solar photovoltaic power plant in the Pap district of Namangan region. |
450.0 |
RP-144 dated 02.05.2023 |
500 МW |
2024-2025 |
211,8 |
145,8 | 73,9 | 50,7 |
7. |
Construction of a new lime plant as part of the Development of the "Yoshlik I" mine. |
99.9 |
RP-2807 dated 01.03.2017, RP-4731 dated 02.05.2020 |
737 thousand tons of lime |
2023-2024 |
51,0 |
23,3 | 27,1 | 116,4 |
8. |
Construction of a solar power plant for the needs of AMMC. |
75.0 |
RP-57 dated 16.02.2023 |
60 MW |
2024-2025 |
70,0 |
15,7 | ||
9. |
Construction of a substation on the territory of Yunusobod city and a 110 Kv network cable. |
16.7 |
RP-91 dated 11.03.2023 |
2х63 МWА |
2023-2024 |
16,7 |
16,7 | 9,9 | 59,6 |
10 |
Joint ventures organized in cooperation with Almalyk MMC JSC and purchase of special mining equipment |
77.1 |
2023-2024 |
70,8 |
30,0 | 44,9 | 149,8 |
-
Information on investment projects implemented by Almalyk MMC JSC in January-December 2023
-
Information on investment projects implemented by Almalyk MMC JSC in January-September 2023
-
INFORMATION on investment projects implemented by Almalyk MMC JSC in January-June 2023
-
INFORMATION on investment projects implemented by Almalyk MMC JSC in January-March 2023
-
INFORMATION on investment projects implemented by Almalyk MMC JSC (01.04.2024)
-
Information on investment projects implemented by Almalyk MMC JSC in January-June 2024
-
Information on investment projects implemented by Almalyk MMC JSC in January-September 2024