REFERENCE
regarding the project of acquisition of “Yoshlik I” mine
of “Almalyk MMC” JSC
01.10.2024
Basis: Resolution No PD-4731 dated may 26, 2020 of the President of the Republic of Uzbekistan “on additional measures to expand the production of non-ferrous and precious metals at “Almalyk MMC” JSC”
Project power: annually 917 thousand ton of copper concentrate and 2,5 thousand ton of molybdenum concentrate.
Project amount: 4 620,4 million dollar
Foreign partner: “Gazprombank” (Russia), “International development projects” (Russia).
Location: Tashkent region, Almalyk city, “Almalyk MMC” JSC.
Raw material base: Products obtained from copper-molybdenum concentrate (copper cathode, gold, silver) produced by the processing of “Yoshlik-1” mine ores, Kalmakyr.
Number of created workplaces: 5 647 pcs
Electricity consumption volume: annual 568,7 mln KWt/s
Gas consumption volume: annual 3,3 mln m3
Commodity product: annual 3 594,5 mlrd soʻm
Export indicators: annual 241,6 mln dollar
Project implementation deadlines: 2017-2025 years
1. TSOT- construction of a mining facility.
At TSOT- the construction site of the mine 5,47 mln m3 (99,6 percent) soil works, 21,7 thousand ton (95 percent) reinforcement and 141,7 thousand m3 (94 percent) concrete works have been performed, 1 205 pcs (91 percent) stav, 19,0 thousand pcs (88 percent) support rollers and 10,4 thousand m (59 percent) conveyor belt have been installed, 429 pcs workers and 34 pcs special vehicles have been involved in construction works.
TSOT- within the mine construction project 74% of the construction and assembly works have been completed, including:
For grinding-loading device (DPU) No 1 the works have been completed in 67 percent, herein concrete works – 96 percent, metal constructions 4 percent and main process equipment installation 72 percent;
For grinding-loading device (DPU) No 2 the works have been completed in 71 percent, herein concrete works – 97 percent, metal constructions – 40 percent and main process equipment installation – 74 percent;
For grinding-loading device (DPU) No 3 the works have been completed in 98 percent, herein concrete works – 99 percent, metal constructions – 100 percent and main process equipment installation – 99 percent;
For surface conveyor branded 302100-CV-101 the works have been completed in 92 percent, herein the concrete works - 99 percent, metal constructions - 89 percent and main process equipment installation - 99 percent;
For surface conveyor branded 302100-CV-201 the works have been completed in 46 percent, herein the concrete works - 99 percent, metal constructions 30 percent.
1.1. Delivery of basic technological equipment.
The construction site was delivered 3 pcs “Uralmashzavod” (Russia) KKD 1500x200 primary grinder, 6 sets “AUMUND” (Germany) plate supplier, main spare parts for 2 sets “THYSSENKRUPP” (Germany) main and 3 sets loading conveyors were partly delivered. Also, 6 pcs bridge cranes and 27 pcs electrical wires of “URALKRAN” (Russia), 3 sets hydraulic hammer manipulator device of “Technopark Impuls”, 3 pcs console crane of “PF ASK” (Russia) and 3 sets dust cleaning system of “ASPEX” (Russia), 3 sets air compressor system of CHKZ (Russia), 5 sets drainage pump of “WEIR” (Turkey), 1 collection 35/10kV substation of “TEXNOKONT” (Kazakhstan), 3 sets accepting bunker dust suppression system of “EIM injiniring” (Russia), 3 sets air circulating system of “VENKON” (Russia).
2. Construction of Copper beneficiation plant No 3.
The construction works of Copper beneficiation plant No 3 are being implemented by the consortium of “Almalyk MMC” JSC and “Uralmashzavod” OJSC as well as “Enter Engineering” with the terms and conditions of “Delivery ready for use”.
“Worley Parsons” foreign company was involved to carry out technical control in the construction.
In the construction site 741,0 thousand m3 (95 percent) concrete works, 104,6 thousand tonn (99 percent) reinforcement works have been completed, 25,1 thousand tonn (67 percent) process equipment and 46,8 thousand tonn (78 percent) metall constructions have been installed.
Within the framework of Copper concentrator plant No 3, the construction and installation works have been fulfilled in - 63 percent, including:
The works for large crushed ore deposit (CKDR) have been fulfilled in 94 percent, herein the concrete works - 100 percent, metal constructions installation – 98 percent and main process equipment installation - 95 percent;
The works for medium crushing building (KSD) have been completed in 89 percent, herein concrete works – 100 percent, metal constructions installation - 92 percent and main process equipment installation - 99 percent;
The works for middle mining building (KSG) have been completed in 84 percent, herein concrete works - 100 percent, metal constructions installation - 94 percent and main process equipment installation 91 percent;
The works for small mining building (KMD) have been completed in 83 percent, herein concrete works – 100 percent, metal constructions installation 92 percent are about to be started
and main process equipment installation has been done- 72 percent;
The works for small mining building (KMG) have been completed in
82 percent, herein concrete works – 100 percent, metal constructions installation 84 percent and main process equipment installation 50 percent;
The works for Mine preparation building (KRP) have been completed in 66 percent, herein concrete works – 96 percent, metal constructions installation 90 percent and main process equipment installation 62 percent;
The works for Main flotation building have been completed in - 48 percent, herein concrete works – 98 percent, metal constructions installation -53 percent and main process equipment installation - 60 percent;
The works for Copper-molybdenum concentrate condensing section have been completed in 67 percent, herein concrete works – 99 percent, metal constructions installation 54% and main process equipment installation – 93 percent;
The works for Filtration and concentrate loading building have been completed in 68 percent, herein concrete works – 100 percent, metal constructions installation 73 percent, and main process equipment installation 64%;
The works for 1st main reducing substation (GPP) have been completed in 98 percent, herein concrete works, metal constructions installation and main process equipment installation – 100 percent, laying electric cables – 83 percent, the installation of the fire alarm system is about to begin;
The works for 2nd main reducing substation (GPP) have been completed in 80 percent, herein concrete works, metal constructions installation – 100 percent, main process equipment installation - 92 percent, laying electric cables -19 percent, the installation of the fire alarm system is about to begin;
The works for 3rd main reducing substation (GPP) have been completed in 96 percent, herein concrete works , metal constructions installation and main process equipment installation – 100 percent, laying electric cables – 71 percent, the installation of the fire alarm system is about to begin;
Administrative and household building (ABK) have been completed in 84 percent, Administrative building (BK) have been completed in 86 percent.
Copper concentrator plant No 3 involved totally 14 121 psc workers (excluding support staff and metal construction site workers) and 820 pcs special vehicles.
2.1. Delivery of basic technological equipment.
For large crushed ore deposit (CKDR) 36 sets electric wires of “URALKRAN”, 2 sets air suction system of “ASPEX” (Russia), 16 sets tape conveyor of “AUMUND”, 2 sets belt conveyor of “PTM” and 8 sets drainage pump of “WEIR” have been delivered.
For middle grinding building (KSD) 8 ta KSD 3000/1500 branded cone grinder of “Uralmashzavod”, 2 sets bridge electric crane of “URALKRAN”, 8 set air suction system of “ASPEX” and 6 pcs drainage pump of “WEIR”, 8 sets belt conveyor of “PTM”, 9 sets electric wires of “URALKRAN”, 16 set belt conveyor of “AUMUND” have been delivered.
For middle mining building (KSG) 8 pcs oscillating gallows of “Pnevmash”, 4 sets air suction system of “ASPEX”, 16 sets belt conveyer of “PTM”, 4 sets trolley unloading conveyor of “BMX RUS”, 5 sets drainage pump of “WEIR”, 47 sets electric wires of “URALKRAN”, 2 sets bridge electric crane and 16 sets belt conveyor of “AUMUND” have been delivered.
For small mining building (KMD) 2 set bridge electric crane and 17 set electric wires of “URALKRAN”, 8 sets belt conveyor of “PTM”, 6 sets belt conveyor of “BMX RUS”, 5 pcs drainage pump of “WEIR” and 6 sets air suction system of “ASPEX” and 6 sets high pressure roller pressing equipment (HPGR) of “THYSSENKRUPP” (Germany) have been delivered.
For small mining building (KMG) 24 sets tertiary miner of “Kwatani” (SEVER MINERALS, South Africa), 4 sets bridge electric crane and 37 sets electric wires of “URALKRAN”, 2 sets belt conveyor of “PTM”, 2 sets belt conveyor and 4 sets trolley unloading conveyor of “BMX RUS” and 6 pcs drainage pump of “WEIR” have been delivered.
For mine preparation building (KRP) 12 sets ball mill (MSHTS) of “UZTM-KARTEKS” have been delivered and the supply of mill lining continues, 47 sets gravity shield of “Kwatani” (SEVER MINERALS, South Africa), 6 sets bridge and 72 sets electric cranes of “URALKRAN”, 24 pcs drainage pump and 12 sets hydro-cyclone of “WEIR”, 32 sets gravity concentrator for the mills of “INTERTECH” (Serbiya) have been delivered.
Moreover, for ball mill 12 sets hydrostatic bearings of “CEMTEC” (Austria), 12 sets toothed crown of “CEMTEC” (Germany), 25 sets mill engine and 12 sets chiller of “ABB Switzerland Ltd”, cylindrical butara for 12 sets mill of “NAIPU” (China), 12 sets automatic ball loader of “DALIAN LEVVIE” (China) and 2 sets of shell (lining) replacement machine and 3 sets bolt removal hammer of “GEARS MINING” (Australia) have been delivered.
For Copper-molybdenum concentrate condensing section 6 sets vertical mill for condensers and all 2 sets filters (Mo) of “Metso:Outotec” (Austria), 5 sets filters (Su) of “Metso:Outotec” (Finland), 6 sets with 17 meters, 2 sets with 28 meters and 1 sets with 5 meters capacities for condensers of “Metso:Outotec” (China), main equipment for all condensers of “Metso:Outotec” (Europe) have been delivered.
For Main flotation building main equipment for the capacities for 6- floatation line of “Metso:Outotec” (China) and 6- floatation line of “Metso:Outotec” (Europe) and 5 sets bridge electric crane (Russia) of “URALKRAN” have been delivered.
For reducing substations No 1, 2, 3 (GPP) 15 sets of KTP (batch transformer substation) “TEXNOKONT” (Kazakhstan) have been delivered.
For main factory part (OZX) 5 sets air compressor system and 1 set air compressor of “Airpol” (Poland), 3 lines of water cooling tower of “Seagull” (China), first batch of Lime milk factory have been delivered, the final 2nd batch will be delivered by “Yilmaz Proses Teknolojileri” (Turkey) by September of this year. Also, 6 sets fire fighting pump station of “WILO” (India), 1 set wastewater treatment plant of “Akvabiom” (Russia) have been delivered.
9 pcs water pump for sealants of “Wilo pumping systems” LLC (Tashkent); 40 pcs hydraulic pumps and 3 pcs GSW pump of “Sulzer Pumps” (Finland), 3 pcs cooling water pump of “V-Flo”ning (China) and for disposal of residuals 3 pcs, for process water pump stations of “Zhejang KEER Pump” (China) 3 pcs and raw water system 26 pcs, for reagent system 108 pcs pumps have been delivered.
3. Construction of the 3rd-Copper concentrator plant’s infrastructure.
In a waste storage facility (1st map) for the construction of the foundation of the dam 17,5 mln m3 (31 percent) (from this 9,2 mln m3 for construction of dam) soil works have been done and 11,0 thousand m (38 percent) pipe have been laid. For these works 273 pcs workers and 327 pcs special vehicles have been involved.
External water supply facilities are in the construction site 77,4 km (69 percent) water pipes have been laid, also, 120 pcs (100 percent) well drilling works, 1,39 mln m3 (75 percent) soil works, 3,0 thousand ton (71 percent) reinforcement, 15,5 thousand m3 (57 percent) concrete works have been done. For these works 141 pcs workers and 49 pcs special vehicles have been involved.
At the moment, construction of 3rd-Copper concentrator plan and its infrastructure facilities and its infrastructure facilities in total 14 964 pcs workers (excluding support staff and metal construction site workers) and 1 229 pcs special vehicles have been involved.
4. Attracting financing.
1,0 billion dollars debt money resources from “Gazprombank” have been involved, within the perimeter of project office facilities 678,0 mln dollar have been used.
A loan agreement for attracting financing was signed with “International development projects” company in the amount of 712,0 mln euro, based on this, 295,2 mln euro euro have been chosen (selected) (319,6 mln dollar ekv.).
Within YeRS agreements concluded for the construction of 3rd-Copper concentrator plan, Waste storage facility (1-map) and External water supply facilities total 1 782,9 mln dollar (153,0 mln dollar with VAT), including in the section of facilities for 3rd-Copper concentrator plan 1 606,9 mln dollar, for Waste storage facility (1-map) 76,6 mln dollar and for External water supply 99,4 mln dollar payments have been done.
5. Works carried out within the perimeter of project office objects:
- In accordance with the assignment No 26/1-410 dated october 27, 2023 Primer Ministers of the Republic of Uzbekistan, the construction and assembly works by mobilizing all relevant resources (manpower and special equipment) should be completed and by december 31, 2024 taking measures to start the factory at full capacity.
- In accordance with the protocol No 200 dated November 9, 2023 (registered under No VM-1218 dated 09.11.2023) held at the Chairmanship of the Prime minister of the Republic of Uzbekistan and the protocol 106 november 29, 2023 of the commission of the Government for investment attraction, industrial development and trade regulation issues (registered under No 04-01-149 dated 30.11.2023) by the end of 2024, the project of “Yoshlik I” mine should fully been put into operation.
- Protocol No 107 dated november 16, 2023 of the meeting of the Commission of the Cabinet of Ministers states that the paragraph 42.2 related to putting 3rd-Copper concentrator plan into operation having recycling power of 60 mln tn of ore annually as per the decree No PF-27 dated february 28, 2023 of the President of the Republic of Uzbekistan should be extended by december 31, 2024.
- In accordance with the “Road map” for accelerating the construction of 3rd-Copper concentrator plan and its infrastructure facility (assignment No 26/1-410 dated february 10, 2024) 2024, taking actions for putting the factory into operation by the end of the year.
- According to the decree No PF-37 dated february 21, 2024 of the President of the Republic of Uzbekistan and minute of the meeting No 26 dated March 16, 2024 commission of the Cabinet of Ministers, on october 2024 the factory should be put into operation.
6. Main problems:
For TSOT-ore:
- By october 20, 2024 for TSOT-ore conveyer system, “FLSmidth” company shall deliver the remained equipment (RIO shelves, 5 pcs recoil drums).
- By october 20, 2024 completing CV-101 main conveyor works to electrical rooms, the power should be provided from KTP-403207 substation.
- By october 30, 2024 remained 308 tn (No 3 unloading conveyor, No. 1 main conveyor, for guide boards for 5.5 tn lining) metall constructions should be prepared.
For 3rd-copper beneficiary plant:
- By october of this year materials (cable, control and measuring devices (CMD), lining, pipes, pumps, shut-off and control valves (ZRA), etc.) should be delivered.
- More than 4 thousand workers, including 3 thousand workers should be involved on october.
According to the waste storage facility (Map 1):
- It is necessary to deliver lined pipes and rods, shut-off valves, compensators and other materials;
- Today, the volume of earthworks required for the construction of the dam is 28 million m3, in order to complete the works, it is necessary to carry out earthworks in the volume of 2.6 million m3 per month starting from october of this year, for this purpose, the mobilization of additional 490 special equipment and fuel and consumables should be provided.
For external water supply:
- Equipment and materials (110/10 kW, 35/6 kW substation, shut-off and control valves (ZRA), control-measuring devices and automation (CMD), electricity) shall be delivered by “Enter Engineering” by September of this year;
- Provision of at least 600 additional workers and 90 special equipment at the construction site.
7. Construction of a quarry and construction of its production infrastructure at the "Yoshlik I" mine.
From the start of the quarry construction project:
201,9 mln m3 (from the beginning of the year 28,0 mln m3) works on opening the surface of the mine have been performed (works have been organized in 2 shift, 1 800 pcs workers and 400 pcs vehicles are working) and 41,63 km railways have been laid;
602 pcs (466,0 mln dollar) mine vehicles (54 pcs 130 tonn, 29 pcs 220 tonn BelAZ and 5 pcs NMT-240 TEREX-KRANTAS 220 tonn dump truck, 33 pcs excavator, 23 pcs drilling equipment, 12 pcs mixing and charing machines) 254 pcs railway vehicles (1 pcs electric locomotive, 5 pcs locomotive, 212 pcs dumpcar, 7 pcs road construction vehicles) as well as 192 pcs auxiliary equipment) have been purchased.
Cyclic flow technology (“TSPT - 2 herd”)
More than 5.9 million m3 (80.8 percent compared to the plan) of earthworks were carried out for the construction of Cyclic Flow Technology ("TSPT-poroda"), which transports more than 20 million m3 of loose rock bodies per year;
"TMX Consulting Ltd" was declared the winner of the tender as a result of the TTT review from the participants and on the basis of the procurement commission's report No. 357007 dated July 12, 2024.
Today, negotiations are underway with the winning company.
Mining industrial site:
- The project documents for the construction of industrial sites "Yoshlik I" and "Kalmaqir" mine TK-1 and TK-2 were presented by the chief designer.
- The ground work of the "Yoshlik I" industrial site has been completed. The perimeter barrier wall is 100 percent completed.
The foundation part of the buildings is 85 percent completed.
- 1.2 km leading to "Kalmakyr" industrial site. the road is completely completed. At present, "Yoshlik I" pit and trench excavation work is 80 percent completed.
The perimeter fence of the "Kalmakyr" industrial site has been completed 100 percent.
- The project documents for the construction of GSHO industrial site were presented by the chief designer.
Construction of buildings and facilities is 90 percent completed.
Currently, the equipment and facilities of the buildings are being brought.
The project documents were completed by the joint venture "Oz'elektroapparat-Electroshield", the contractor for the TP-8 and TP-9 substations, which provide electricity to the cyclic flow technology equipment that transports the mine and loose rock bodies. Construction works will be completed and commissioned by the contracting organization in 2024.
The preparation of the vertical area for the construction of "TN-8" has been completed and the documents have been submitted.
- 2 pcs 80 MVA transformers are installed.
100 percent of the construction and assembly works have been completed.
It was launched on august 30 of this year.
- The preparation of the vertical area for the construction of "TN-9" has been completed and the documents have been submitted.
- 2 pcs 63 MWA transformers have been installed.
100 percent of the construction and assembly works have been completed.
It is expected to be launched in october this year.
8. Construction of an external power supply facility with a capacity of 650 megawatts
The construction of 10 km of 500 kV power line by the joint venture "Oz'elektroapparat-Electroshield" for the construction of power supply facilities was completed 100 percent.
Also, 100 percent of the construction and installation works and delivery of the main equipment at the 500 kV digital substation were completed. The facility will be completed in december 2023, and is currently being networked and configured.
9. Reconstruction of the explosive factory and explosive materials warehouse:
Main production technological devices: 13 capacities installed 100 percent, technological modules completed 100 percent and compressors and steam generators installed, construction of buildings and facilities continues.
Purchase and installation of auxiliary equipment and devices (external power supply, transformers, external and internal water supply, technological waste water treatment facility, additional railway crossings, road infrastructure, storage of auxiliary materials - distribution warehouses and water heating system) works are being carried out.
It will be launched in december this year.
10. Temporary cars and railways
The construction of external communications and temporary railway traces is underway.
Total 45.6 km as per technical and economic basis. It is planned to build railways 01.07.2024y. As of now, the total cost of construction works is 132.65 billion. 41.48 km of railways were fully built and electrified.
MPTS (microprocessor centralization of signals and arrows) and ESSO (electronic system of axle counting) of "Kalmakyr and Kolsevaya stations and the peregon between them", "Svinsovaya station", "Otvalnaya station" and "Fabrichnaya station" will be launched this year.
In accordance with the minute of the meeting 106 dated november 29, 2023 (registered under 04-01-149 dated 30.11.2023) commission of the government for issues for involving the investments, developing the industry and regulating trade and No 200 dated November 9, 2023 held on the chairman of the Primer minister of the Republic of Uzbekistan (registered under No VM-1218 dated 09.11.2023):
- On may 2024 complete the construction and installation works of the line 1 of the 3rd copper beneficiary plant;
- by the end of 2024 launch of the Yoshlik I mine development project (Phase I, Phase 1) at full capacity.
Works to be implemented.
Together with the Ministries of Mining and geology and investments, Industry and trade “Development of Yoshlik I mine” until the end of the year on the strategic investment project 1179,0 mln dollar including “according to the Yoshlik I mine development project 244,0 mln dollar additional measures were determined in order to ensure the appropriation of funds and the start-up of facilities within the specified periods.
Construction of a quarry and construction of its production infrastructure at the "Yoshlik I" mine.
1) Another 32.0 million m3 of mining will be completed by the end of this year.
2) By the end of this year, the following objects of the mining complex and infrastructure will be commissioned:
"Yoshlik I" quarry, Explosive materials factory, ASU GTK, “TN-8”, “TN-9”, 8,2 km internal highways, 4,12 km internal quarry railways will be built and electrified, 4 railway station microprocessor center and electronic axle counting system, sample cutting and analysis laboratory.
3) Construction works will be carried out by the end of the year on the Cyclic flow technology ("TSPT-poroda") carrying loose rock bodies.
-
Almalyk MMC JSC strategic development report (01.10.2022y.)
-
Almalyk MMC JSC Strategic Development Report (02.06.2022y.)
-
Almalyk MMC JSC strategic development report (01.12.2022y.)
-
Almalyk MMC JSC strategic development report (01.01.2023y.)
-
Almalyk MMC JSC strategic development report (01.07.2023y.)
-
Almalyk MMC JSC strategic development of report (01.10.2023y.)
-
Almalyk MMC JSC strategic development report (01.01.2024y.)
-
Almalyk MMC JSC strategic development report (01.07.2024 y.)
-
Almalyk MMC JSC strategic development report (01.10.2024 y.)