Рус O'z En
Helpline
Feedback

The results of 6 months in the union are significant

18 July 2022, 11:30 1578

For the development of every enterprise, it is very important to fulfill the tasks of the plan. The basis of timely achievement of these indicators is the labor efficiency of employees.

Production indicators in a number of enterprises of Almalyk Mining and Metallurgical Complex recorded high results. In particular, the scientific-production association for the production of rare metals and hard alloys under the control of the complex is one of them.

By the labor team, the task of production of goods was fulfilled by 196.6 percent.

566.1 tons of molybdenum 3 oxide were produced, and the plan was completed by 111.6 percent.

Production of molybdenum rods and briquettes reached 377.2 tons.

The result of production of refractory ceramic products was 505.4 tons, 129.3 percent of the plan, and 125.6 percent growth compared to last year.

Production of molybdenum metal using the production capacities was completed by 110.3 percent.

In total, products worth 205 billion soums were produced by the efforts of Union workers.

In addition, the association fulfilled the export plan by 384 percent and exported products worth 18 million dollars.

Based on the localization program, 42 projects worth 109 billion soums are being implemented.

It is worth noting that the program for the development of the "Union of scientific production of rare metals and hard alloys" and the development of new products of "Almalyk Mining and Metallurgical Complex " JSC for 2022-2024 has been developed.

According to the program, it is planned to implement 33 projects with a total value of 82.35 million dollars in 4 directions at this enterprise.

As a result, by 2024, an additional 3.9 trillion soums of goods will be produced, 300 new jobs will be created.

Currently, 33 percent of the works in the section of the routes have been completed, in particular, 5 projects have been almost completely completed and commissioned.

In addition, electricity efficiency has also been achieved in the union. During 6 months, 2.8 billion soums of energy were saved, and compared to January-June 2021, a growth rate of 144.5 percent was observed.

Reconstruction works in joint workshops, installation of new compressors and boilers became important in achieving electricity savings.

Also, the maximum hour to minimum hour principle was applied in the hydrogen section, where the most electricity is used.

By the end of 2022, the labor team has set high goals. In particular, it is planned to produce a number of new types of products within the framework of the copper industry cluster. In short, the adoption of new products serves the development of another direction.

Information service

Share your:
Text to speech