Results of production activity for 8 months of the year 2023

06 September 2023, 10:37 945

During January-August of this year, the workforce of the Almalyk Mining and Metallurgical Combine completed all production tasks.

Thus, according to data provided by the production and cost monitoring department of AMMC, since the beginning of the year the plant has ensured the production of marketable products by 102.3%.

The forecast indicator for ore production by the Kalmakyr mine management was fulfilled by 101.1%, the growth rate in this direction was 104.3%.

The forecast for the processing of copper raw materials was fulfilled by 100.4%, the growth rate was 105%. The work teams of the copper concentration plant and copper concentration plant-2 completed the tasks assigned to them by 100% and 103.7%, respectively.

During the reporting period, the fulfillment of the forecast indicator for copper content in concentrate was 106.6%, the growth rate was 106.5%. It is worth emphasizing that the teams of Copper Concentrator and Copper Concentrator-2 noted high results in this direction - 103.5% and 129.5%, respectively.

High growth rates have also been achieved in the production of copper cathode, zinc metal and sulfuric acid. The forecast for the production of metallic zinc from our own raw materials was fulfilled by 101.8%.

Over the 8 months of this year, the assignments for the extraction and processing of polymetallic ore by the Khandiza mine management were completed by 104.5% and 103.6% (103.8%), the zinc content in the zinc concentrate was 101.4%.

Extraction of gold ore was carried out: Angren mine management - by 102.8%, Chadak mine management - by 101.1%, Kauldy mine - by 104.7%, its processing - by 103.5%, 100.5%, 106.6%, respectively. The indicators for the content of the first and second metals in the concentrate were fulfilled. The content of the first metal in the concentrate was: ARU - 102.7%, ChRU - 100.4%, Kauldy mine - 110.9%; second metal content: ARU - 133.7%, ChRU - 173.2%, Kauldy mine - 111.3%.

In addition, tasks for the production of copper sulfate (100%), enamel wire (100%), technical selenium and technical tellurium (100%), ammonium perranate (101.8%), palladium powder (101.6%) and molybdenum trioxide were completed (110.1%).