8 month results in Almalyk Mining and Metallurgical Complex are high

06 September 2022, 8:45 1645

As of January-August 2022, all production indicators were fulfilled by the work team of the Almalyk mining and metallurgical Complex.

In particular, 114.8percent of the planned task of production of goods was fulfilled.

100.2percent of the plan was achieved in the mining of ore at the Kalmokgyr mine.

A growth rate of 100.1percent was recorded in the processing of copper raw materials. In this direction, a growth rate of 100.1percent was achieved at the Copper Enrichment Factory. In the 2nd copper enrichment factory, the plan was achieved by 100.9 percent and a growth rate of 100.5percent was observed.

In the concentrate, the copper plan was fulfilled by 100.8percent.

All forecasts for the production of copper cathode have been fulfilled. In this direction, the plan has been completed 100 percent.

Zinc metal production plan was fulfilled by 101.6 percent, growth rate was 100.9 percent.

Regarding the production of zinc metal from our own raw materials, the planned task was fulfilled by 106.3 percent and a growth rate of 130.9 percent was observed.

The production plan of sulfuric acid was completed by 105.9 percent. The growth rate was 105.3 percent. A result of 105.8 percent was recorded in the plan and growth rate of sulfuric acid production at the copper smelter.

At the zinc plant, the plan was fulfilled by 106.7 percent and a growth rate of 101.9 percent was achieved.

The production plan of copper copper, enameled copper wires, technical selenium, technical tellurium is 100 percent fulfilled.

The plan for the production of copper pipes, which is an export product, has been completed by 109.7 percent.

The production plan of perranate ammonium was fulfilled by 137.3 percent, and the plan for the production of molybdenum 3 oxide by 114.6 percent.

We can see in the following figures that the labor teams of the underground mines within the Complex have also fulfilled the specified tasks.

Khandiza Mining Department

Polymetallic ore mining – 101,6 percent.

Polymetallic ore processing – 101,9 percent, growth rate – 101,1 percent.

Zinc content in zinc concentrate – 114,9 percent.

Angren Mining Department

Mining of gold-bearing ore – 103,4 percent.

Ore processing – 103,3 percent.

First metal in concentrate – 104,0 percent.

Second metal in concentrate – 132,6 percent.

Chodak Mining Department

Mining of gold-bearing ore – 102,7 percent. Growth rate – 100 percent.

Ore processing – 102,5 percent.

First metal in concentrate – 102,1 percent.

Second metal in concentrate – 130,8 percent.

Kovuldi Mining department

Mining of gold-bearing ore – 100,4 percent. Growth rate – 118,1 percent.

Ore processing – 100,2 percent. Growth rate – 126,1 percent

First metal in concentrate – 103,1 percent.

Second metal in concentrate – 104,5 percent. Growth rate 111,9 percent.