In 2022, Almalyk Mining and Metallurgical Complex produced commercial products worth 30.5 trillion UZS.
The head of the information service of AMMC, Umida Karshiboeva, spoke about this at the briefing at AMMC.
The AMMC staff has fulfilled all the production targets set for 2022.
In particular, in 2022, commercial products worth 30.5 trillion UZS were produced (the forecast was 28 trillion UZS). The task in this direction was fulfilled by 108.3%.
In terms of products:
copper cathode – 148,516 tons (design capacity – 148,000 tons);
metal zinc – 90.05 thousand tons;
sulfuric acid – 815.0 thousand tons.
Forecasts for precious metals fulfilled for:
gold – 100.3%;
silver – 100.3%.
Rare metals produced:
molybdenum – 1,177.2 tons;
tungsten – 33.8 tons;
selenium – 34.5 tons;
tellurium – 2.8 tons;
palladium – 92.5 kg.
As part of the investment program, 788.8 million USD were utilized from own funds and loans. Compared to the previous year, an increase of 1.7 times was noted in this direction. 15 projects had been implemented with a total value of 1.3 trillion UZS, including the commissioning of 5 social facilities (worth 116.1 billion UZS).
During the reporting period, products totaling 947.5 million US dollars were exported, the forecast was fulfilled by 110.8%.
In the framework of the Localization Program, products worth 334.1 billion UZS were produced (the forecast was fulfilled by 141.0%).
As part of the Digitalization Program, 48 information systems were introduced aimed at automating the production processes, the paper document flow was reduced by 80%, as well as the volume of inventory balances (by 260 billion UZS), saving a total of 237 billion UZS.
In 2022, AMMC made payments to the state budget in the amount of 18.6 trillion UZS, and to social funds in the amount of 240.3 billion UZS.